PSE&G Begins Underground Construction in Ridgefield Park as part of Northeast Grid Electric Reliability Project

(Newark, NJ – August 18, 2014) Public Service Electric and Gas Co. (PSE&G) has begun construction through Ridgefield Park as part of the utility’s Northeast Grid Electric Reliability Project. The utility will be installing 15 miles of new 230,000 kilo-volt (230kV) underground electric transmission circuit from its Athenia Switching Station in Clifton to the Bergen Switching Station in Ridgefield. The underground route in Ridgefield Park runs from Railroad Ave. to Mt. Vernon St. to Teaneck Rd. to the Bergen Turnpike. Manhole installation construction began on August 18, 2014. Trenching and conduit installation is expected to begin on or about September 15, 2014.