Bernards Township
Q4 2020
We have completed surveying of the right-of-way, along with verifying subsurface conditions and underground utilities. You may see our crews on the right-of-way building temporary access roads needed to execute construction and building foundations for the new structures.
Safety is our highest priority at PSE&G, and it is essential that you and anyone occupying your property refrain from going on the right-of-way during these activities.
PLEASE NOTE: Maintaining proper tree clearance from the power lines is absolutely necessary to assure:
The continued safety of homeowners living near the transmission lines,
The safety of PSE&G employees and contractors working on the power lines, and
The reliability of the electric utility system.
In order to maintain PSE&G’s facilities, the cutting and/or mowing of vegetation brush may be necessary on the transmission right-of-way that crosses your property. Every effort will be made to minimize the impact on your property.
.
|
Branchburg
Q1 2021
You may see our crews on the right-of-way building temporary access roads needed to execute construction and building foundations for the new structures. Once completed, we will be erecting the “Y” monopoles. The new transmission structures may be offset from the existing towers, but will remain within the limits of the ROW. Please be aware that equipment and materials, including steel for the replacement structures, may be stored and partially assembled on the right-of-way at various times during the construction period. We will also begin the process of removing wire from the exisiting lattice structures. Road closures will be necessary for this process.
Safety is our highest priority at PSE&G, and it is essential that you and anyone occupying your property refrain from going on the right-of-way during these activities.
|
Bridgewater
Q4 2021
We have completed surveying of the right-of-way, along with verifying subsurface conditions and underground utilities. On or about the middle November, you may see our crews on the right-of-way installing temporary access roads. These temporary access roads, either stone or timber matting, allow for our construction traffic and work locations around each transmission structure. All construction activity will take place within the limits of the ROW.
Once completed, contractors will begin installation of the foundations for the new “Y” monopoles. These new “Y” monopoles may shift along the centerline of the existing lattice towers, but will remain within the ROW. This work may generate some unavoidable noise and vibration. In addition, our contractors will begin the process of removing the wires from the existing structure. Road closures will be needed for this process.
Pursuant to the Bridgewater construction office, work hours will be Monday – Friday, 7:30 a.m. - 6 p.m. and Saturday, 8 a.m. - 4 p.m. All construction activity will take place within the limits of the ROW.
Safety is our highest priority at PSE&G, and it is essential that you and anyone occupying your property refrain from going on the right-of-way during these activities.
PLEASE NOTE: Maintaining proper tree clearance from the power lines is absolutely necessary to assure:
- The continued safety of homeowners living near the transmission lines,
- The safety of PSE&G employees and contractors working on the power lines, and
- The reliability of the electric utility system.
In order to maintain PSE&G’s facilities, the cutting and/or mowing of vegetation brush may be necessary on the transmission right-of-way that crosses your property. Every effort will be made to minimize the impact on your property.
|
Chatham Borough
Q4 2021
We will begin installation of the foundations for the new “Y” monopoles. These new “Y” monopoles may shift along the centerline of the existing lattice towers. There may be some unavoidable noise and vibrations during the drilling phase of construction. The drilling phase is anticipated to last for about three days, weather permitting. We understand this may be an inconvenience.
PLEASE NOTE: Maintaining proper tree clearance from the power lines is absolutely necessary to assure:
- The continued safety of homeowners living near the transmission lines,
- The safety of PSE&G employees and contractors working on the power lines, and
- The reliability of the electric utility system.
In order to maintain PSE&G’s facilities, the cutting and/or mowing of vegetation brush may be necessary on the transmission right-of-way that crosses your property. Every effort will be made to minimize the impact on your property.
|
Chatham Township
Q4 2021
On or about Friday, November 19, 2021, PSE&G and its contractors will utilize helicopter crews to help install the RPV transmission lines in parts of Chatham Township and the Township of Long Hill. The schedule for this activity is an estimated timeframe and may be slightly adjusted.
The helicopter activity is expected to last for two days, from 9 a.m. to 5 p.m., depending on the weather. This activity entails pulling ropes from one transmission structure to the next, using a small helicopter.
On Friday, November 19, brief and intermittent road closures are anticipated along Long Hill Lane (Chatham Twp), Crestwood Rd., Meyersville Rd., Hickory Tavern Rd., Long Hill Rd. and Mountain Ave. On Saturday, November 20, brief and intermittent road closures are anticipated along Crestwood Rd.
Meyersville Rd., Hickory Tavern Rd., Long Hill Rd., Mountain Ave., and Morristown Rd.
PLEASE NOTE: Maintaining proper tree clearance from the power lines is absolutely necessary to assure:
- The continued safety of homeowners living near the transmission lines,
- The safety of PSE&G employees and contractors working on the power lines, and
- The reliability of the electric utility system.
In order to maintain PSE&G’s facilities, the cutting and/or mowing of vegetation brush may be necessary on the transmission right-of-way that crosses your property. Every effort will be made to minimize the impact on your property.
|
East Amwell
Q3 2017 thru Q4 2019
The Roseland – Pleasant Valley Project (RPV) is a $546 million investment designed to strengthen the electric transmission system by replacing older transmission facilities between PSE&G’s Roseland Switching Station in Roseland, N.J., and its Pleasant Valley Switching Station in Hopewell, N.J. On average, these transmission facilities are approximately 90 years old.
You may see our crews on the right-of-way performing geotechnical work and verifying subsurface conditions and underground utilities. In addition, you may see construction activities to support the replacement of the electric infrastructure. Safety is our highest priority at PSE&G, and it is essential that you and anyone occupying your property refrain from going on the right-of-way during these activities.
|
Florham Park
Q1 2021
We have completed surveying of the right-of-way, along with verifying subsurface conditions and underground utilities. On or about February 22, 2021, you may see our crews on the right-of-way installing temporary access roads. These temporary access roads, either stone or timber matting, allow for our construction traffic and work locations around each transmission structure. All construction activity will take place within the limits of the ROW.
Safety is our highest priority at PSE&G, and it is essential that you and anyone occupying your property refrain from going on the right-of-way during this activity.
|
Hillsborough
Q1 2021
You may see our crews on the right-of-way building temporary access roads needed to execute construction and building foundations for the new structures.
Once completed, we will be erecting the “Y” monopoles. The new transmission structures may be offset from the existing towers, but will remain within the limits of the ROW. Please be aware that equipment and materials, including steel for the replacement structures, may be stored and partially assembled on the right-of-way at various times during the construction period. We will also begin the process of removing wire from the exisiting lattice structures. Road closures will be necessary for this process.
Safety is our highest priority at PSE&G, and it is essential that you and anyone occupying your property refrain from going on the right-of-way during these activities.
PLEASE NOTE: Maintaining proper tree clearance from the power lines is absolutely necessary to assure:
The continued safety of homeowners living near the transmission lines,
The safety of PSE&G employees and contractors working on the power lines, and
The reliability of the electric utility system.
In order to maintain PSE&G’s facilities, the cutting and/or mowing of vegetation brush may be necessary on the transmission right-of-way that crosses your property. Every effort will be made to minimize the impact on your property.
|
Hopewell Township
Q3 2017 thru Q4 2019
You may see our crews on the right-of-way performing geotechnical work and verifying subsurface conditions and underground utilities. In addition, you may see construction activities to support the replacement of the electric infrastructure. Safety is our highest priority at PSE&G, and it is essential that you and anyone occupying your property refrain from going on the right-of-way during these activities.
|
Lambertville
Q3 2017 thru Q4 2019
You may see our crews on the right-of-way performing geotechnical work and verifying subsurface conditions and underground utilities. In addition, you may see construction activities to support the replacement of the electric infrastructure. Safety is our highest priority at PSE&G, and it is essential that you and anyone occupying your property refrain from going on the right-of-way during these activities.
|
Livingston
Q4 2020 - Q2 2021
We have completed surveying of the right-of-way, along with verifying subsurface conditions and underground utilities. You may see our crews on the right-of-way building temporary access roads needed to execute construction and building foundations for the new structures. Safety is our highest priority at PSE&G, and it is essential that you and anyone occupying your property refrain from going on the right-of-way during these activities.
Once completed, we will be erecting the “Y” monopoles. The new transmission structures may be offset from the existing towers, but will remain within the limits of the ROW. Please be aware that equipment and materials, including steel for the replacement structures, may be stored and partially assembled on the right-of-way at various times during the construction period. We will also begin the process of removing wire from the exisiting lattice structures. Road closures will be necessary for this process.
On or about Thursday, February 18, 2021, PSE&G and its contractors will utilize helicopter crews to help install the RPV transmission lines between the PSE&G Roseland Switching Station and Old Road. The schedule for this activity is an estimated timeframe and may be slightly adjusted.
The helicopter activity is expected to last for one to four days, from 9 a.m. to 4 p.m., depending on the weather. This activity entails pulling a rope from one transmission structure to the next, using a small helicopter. Brief and intermittent road closures are expected along Dorsa Avenue, Naylon Avenue, and West Mount Pleasant Avenue (State Highway 10).
|
Long Hill Township
Q1 2022
The new conductors are up to design tension and the team will work to secure them to the tower off Mountain Road during the work week of 1/24/2022 -1/29/2022. After wires are secured to the tension structure in the middle, the team will secure the tension towers at either end of the pull . This work is scheduled to last through the first week of February.
The team is targeting the second week of February to secure the wires to the remaining suspension towers out in the middle. During that week, the team is also projecting to install the spacers in the wire.
On or about February 7, 2022, the team will begin construction work on the second phase of the project through Long Hill. You may see our crews on the right-of-way installing temporary access roads south of Morristown Road and through to King George Road. These temporary access roads, either stone or timber matting, allow for our construction traffic and work locations around the 13 existing transmission structures. This activity will likely last until May and will be followed by the installation of the new foundations. The overhead activity is planned to start in the fall of 2022. All construction activity will take place within the limits of the ROW.
Safety is our highest priority at PSE&G, and it is essential that you and anyone occupying your property refrain from going on the right-of-way during these activities.
|
Raritan Township
Q3 2017 thru Q4 2019
The Roseland – Pleasant Valley Project (RPV) is a $546 million investment designed to strengthen the electric transmission system by replacing older transmission facilities between PSE&G’s Roseland Switching Station in Roseland, N.J., and its Pleasant Valley Switching Station in Hopewell, N.J. On average, these transmission facilities are approximately 90 years old.
You may see our crews on the right-of-way performing geotechnical work and verifying subsurface conditions and underground utilities. In addition, you may see construction activities to support the replacement of the electric infrastructure. Safety is our highest priority at PSE&G, and it is essential that you and anyone occupying your property refrain from going on the right-of-way during these activities.
|
Raritan Township
Q1 2021
You may see our crews on the right-of-way building temporary access roads needed to execute construction and building foundations for the new structures.
Once completed, we will be erecting the “Y” monopoles. The new transmission structures may be offset from the existing towers, but will remain within the limits of the ROW. Please be aware that equipment and materials, including steel for the replacement structures, may be stored and partially assembled on the right-of-way at various times during the construction period. We will also begin the process of removing wire from the exisiting lattice structures. Road closures will be necessary for this process.
Safety is our highest priority at PSE&G, and it is essential that you and anyone occupying your property refrain from going on the right-of-way during these activities.
PLEASE NOTE: Maintaining proper tree clearance from the power lines is absolutely necessary to assure:
The continued safety of homeowners living near the transmission lines,
The safety of PSE&G employees and contractors working on the power lines, and
The reliability of the electric utility system.
In order to maintain PSE&G’s facilities, the cutting and/or mowing of vegetation brush may be necessary on the transmission right-of-way that crosses your property. Every effort will be made to minimize the impact on your property.
|
Readington
Q2 2021
You may see our crews on the right-of-way building temporary access roads needed to execute construction and building foundations for the new structures.
Once completed, we will be erecting the “Y” monopoles. The new transmission structures may be offset from the existing towers, but will remain within the limits of the ROW. Please be aware that equipment and materials, including steel for the replacement structures, may be stored and partially assembled on the right-of-way at various times during the construction period. We will also begin the process of removing wire from the exisiting lattice structures. Road closures will be necessary for this process.
Safety is our highest priority at PSE&G, and it is essential that you and anyone occupying your property refrain from going on the right-of-way during these activities.
|
Roseland
Q1 2021
You may see our crews on the right-of-way building temporary access roads needed to execute construction and building foundations for the new structures.
Once completed, we will be erecting the “Y” monopoles. The new transmission structures may be offset from the existing towers, but will remain within the limits of the ROW. Please be aware that equipment and materials, including steel for the replacement structures, may be stored and partially assembled on the right-of-way at various times during the construction period. We will also begin the process of removing wire from the exisiting lattice structures. Road closures will be necessary for this process.
Safety is our highest priority at PSE&G, and it is essential that you and anyone occupying your property refrain from going on the right-of-way during these activities.
PLEASE NOTE: Maintaining proper tree clearance from the power lines is absolutely necessary to assure:
- The continued safety of homeowners living near the transmission lines,
- The safety of PSE&G employees and contractors working on the power lines, and
- The reliability of the electric utility system.
In order to maintain PSE&G’s facilities, the cutting and/or mowing of vegetation brush may be necessary on the transmission right-of-way that crosses your property. Every effort will be made to minimize the impact on your property.
|
Warren Township
Q3 2017 thru Q4 2019
The Roseland – Pleasant Valley Project (RPV) is a $546 million investment designed to strengthen the electric transmission system by replacing older transmission facilities between PSE&G’s Roseland Switching Station in Roseland, N.J., and its Pleasant Valley Switching Station in Hopewell, N.J. On average, these transmission facilities are approximately 90 years old.
You may see our crews on the right-of-way performing geotechnical work and verifying subsurface conditions and underground utilities. In addition, you may see construction activities to support the replacement of the electric infrastructure. Safety is our highest priority at PSE&G, and it is essential that you and anyone occupying your property refrain from going on the right-of-way during these activities.
|
West Amwell
Q3 2017 thru Q4 2019
You may see our crews on the right-of-way performing geotechnical work and verifying subsurface conditions and underground utilities. In addition, you may see construction activities to support the replacement of the electric infrastructure. Safety is our highest priority at PSE&G, and it is essential that you and anyone occupying your property refrain from going on the right-of-way during these activities.
|