Reliability Project Overview

PSE&G is currently conducting statewide electric reliability improvements to its utility infrastructure. These enhancements will improve both electric service reliability and system redundancy to ensure safe and reliable service to our customers. Throughout the state of New Jersey, PSE&G infrastructure upgrades will reduce the demand on the existing 26kV network. The projects will install 69kV transmission circuits connecting PSE&G stations around the state.

Activity Overview

  • New 69kV circuits will connect the Fair Lawn and Paramus stations.
    • The route runs along an existing pole line on South Maple Avenue to Spring Avenue to Hope Street to East Ridgewood Avenue.
  • The existing utility poles will be replaced with taller, sturdier poles that combine new 69kV circuits with existing 26kV, 13kV, or 4kV circuits.
  • Vegetation Management activity such as tree trimming or tree removals may occur in order to allow for the safe installation of new equipment.
  • Pole line reconstruction commenced in the 2nd Quarter of 2013.
  • The project is estimated to be completed by the 4th Quarter of 2014.
  • PSE&G will work with the Township of Ridgewood Police to keep traffic impacts to a minimum.

This route will be approximately 12 miles along the existing public right of ways in the towns of Fair Lawn, Glen Rock, Ridgewood, Paramus, Oradell, New Milford, Dumont and Bergenfield.

For more information on this project, please contact:

Project Hotline - North
1-800-901-5035
Image CAPTCHA
Enter the characters shown in the image.

For media inquiries regarding this project, please contact:

PSE&G's Media Hotline
973-430-7734