Paramus

Reliability Project Overview

PSE&G is currently conducting statewide electric reliability improvements to its utility infrastructure. These enhancements will improve both electric service reliability and system redundancy to ensure safe and reliable service to our customers. Throughout the state of New Jersey, PSE&G infrastructure upgrades will reduce the demand on the existing 26kV network. The projects will install 69kV transmission circuits connecting PSE&G stations around the state.

Activity Overview

  • New 69kV Gas Insulated Switchgear (GIS), which allows for the addition of increased voltage capacity with minimal impact to the existing station footprint, will be installed at our Paramus and Spring Valley substations.
  • New 69kV circuits will connect the Fair Lawn and Paramus stations.
    • The route runs along an existing pole line on East Ridgewood Avenue.
  • New 69kV circuits will connect the Paramus and Dumont stations.
    • The route runs along an existing pole line on East Firehouse Lane to East Ridgewood Avenue/Oradell Avenue to Pascack Road to North Fairview Avenue to Ridgewood Avenue.
  • New 69kV circuits will connect the Fair Lawn and Spring Valley stations.
    • The route runs along an existing pole line on Route 4 West to Ikea Drive to Prospect Street
    • The route runs underground on Prospect Street to Spring Valley Road.
  • New 69kV circuits will connect the Spring Valley Road and Paramus stations.
    • The route runs underground on Spring Valley Road.
    • The route runs along an existing pole line on Spring Valley Road to Century Avenue to Route 17 North 
    • The routs runs underground along Nelson Avenue to Woodland Avenue. 
  • New 69kV circuits will connect the Spring Valley Road and Hasbrouck Heights stations.
    • The route runs underground on Spring Valley Road.
    • The route runs along an existing pole line on Spring Valley Road to Spring Valley Avenue.
  • The existing utility poles will be replaced with taller, sturdier poles that combine new 69kV circuits with existing 26kV, 13kV, or 4kV circuits.
  • Vegetation Management activity such as tree trimming or tree removals may occur in order to allow for the safe installation of new equipment.
  • Pole line reconstruction commenced in the 4th Quarter of 2013.
  • The project is estimated to be completed by the 4th Quarter of 2016.
  • PSE&G will work with the Borough of Paramus Police to keep traffic impacts to a minimum.

This route will be approximately 32 miles along the existing public right of ways in the towns of Fair Lawn, Glen Rock, Ridgewood, Paramus, Oradell, New Milford, Dumont, Bergenfield, Maywood, Lodi, Hackensack, South Hackensack, Teterboro, and Hasbrouck Heights.

For more information on this project, please contact:

Project Hotline
1-800-901-5035
Image CAPTCHA
Enter the characters shown in the image.

For media inquiries regarding this project, please contact:

PSE&G's Media Hotline
973-430-7734
    1. What is 69kV transmission?
    2. What will these projects do?
    3. Why are these upgrades needed?
    4. What type of construction will these projects entail?
    5. How tall will the replacement poles be?
    6. What is the difference between the existing and new line voltage?
    7. How long will construction last?
    8. How will this impact traffic?
    9. What are the benefits to the region?
    10. What approvals are you seeking?
    11. Do the lines produce electric and magnetic fields?
    12. Are electric and magnetic fields (EMFs) harmful?
    13. Who can I contact for more information?

    What is 69kV Transmission?

    69kV transmission lines are the standard of the 21st century, linking higher voltage lines with switching stations and substations. They will ultimately replace and enhance a 50+ year-old system built on 26kV lines, increasing reliability, capacity, and safety.

    What will these projects do?

    PSE&G is currently improving its electric reliability statewide in-order to upgrade its utility infrastructure. PSE&G infrastructure upgrades include the addition of a 69kV network that will alleviate the demand on the existing 26kV network. These upgrades will increase both electric service reliability and system redundancy to ensure safe and reliable electric service to our customers.

    Why are these upgrades needed?

    These upgrades are needed to address the increased demand for reliable electricity throughout PSE&G service territory. As population has increased and consumer electronic needs have evolved, the 26kV legacy networks of the last century have been taxed. The addition of a 69kV network will alleviate the demands on the existing 26kV network.

    What type of construction will these projects entail?

    These projects will install 69kV circuits connecting stations to each other. Underground and Overhead pole line construction is taking place throughout the state. New 69kV circuits are being installed to connect each upgraded station and existing utility poles will be replaced with taller sturdier poles that combine existing 26kV, 13kV, or 4kV circuits. New 69kV Gas Insulator Switchgear (GIS) will also be installed at various stations in multiple municipalities.

    How tall will the replacement poles be?

    The replacement poles will range in height between 57 and 65 feet.

    What is the difference between the existing and new line voltage?

    Existing pole lines throughout the state carry 4kV, 13kV and/or 26kV lines. The new pole lines will carry these existing lines in addition to a new 69kV line for added reliability and capacity.

    How long will construction last?

    As of December 17, 2014 PSE&G has augmented or replaced approximately 209 miles of its 26kV network with 69kV lines in several New Jersey municipalities, all in an effort to ensure that the people of New Jersey have the power they need when they need it. Continued substation and pole line construction is currently scheduled through 2021.

    How will this impact traffic?

    Traffic may be slightly impacted during construction; however PSE&G will work with municipal safety and traffic departments to minimize any traffic issues that arise during construction.

    Safety of the public and construction crews is our highest priority. During construction, it is essential that you and anyone occupying your property, including children and pets, refrain from going near our construction work zones.

    What are the benefits to the region?

    This project will provide safe, highly reliable service.  It will also create construction jobs, and provide municipal revenue though requisite permits. The enhanced electrical infrastructure will help support regional economic growth.

    What approvals are you seeking?

    PSE&G will secure necessary permits and approvals from local governing authorities wherever construction is taking place, as well as the New Jersey Department of Environmental Protection and other applicable state agencies.

    Do the lines produce electric and magnetic fields?

    Electric and magnetic fields are present wherever there is a flow of electric current, whether in wires in the home, electrical appliances, or power lines. Electric fields are produced by the voltage or electrical pressure in a wire and are present even if an appliance is turned off, as long as it is connected to a source of electric power. Magnetic fields are produced whenever there is a flow of electric current through a wire. Electric and magnetic fields are not visible, like other fields such as a gravitational field or a temperature field.

    Are electric and magnetic fields (EMFs) harmful?

    The overwhelming body of scientific study shows no definitive link between EMF and human health issues. Since 1977, concerns over magnetic fields and possible health effects have been the subject of numerous scientific and regulatory review panels, and extensive research and studies continue to be funded in this field of study.

    After nearly 30 years of worldwide research, there are no direct or causal links between electric and magnetic fields and adverse health effects. New Jersey has standards regarding maximum permissible electric fields at the edge of transmission line rights of way. However, there are no state standards with regards to magnetic field levels nor are there any federal rules, regulations or standards for either electric or magnetic field levels.

    Magnetic fields from appliances like hair dryers, microwave ovens, and motorized appliances are often stronger than the fields directly beneath power lines. PSE&G will design and install this line according to appropriate state and federal guidelines related to safety and environmental impact.

    Learn more about EMF 

    Who can I contact for more information?

    If you have questions or concerns, please visit our website at http://psegtransmission.com/reliability-projects/69kV or call our toll free number at 1-800-901-5035 (for Bergen, Passaic, Hudson, Essex, Morris, Somerset, Union, Hunterdon and Middlesex counties) or 1-800-606-0045 (for Mercer, Burlington, Camden or Gloucester counties).

NOTE: Construction schedule information is tentative and subject to change based on several factors, including weather and field conditions.

Paramus

  • November 14, 2016 - November 18, 2016

    No 69kV Pole Set and Wire Work at this time. 

    Excluding inclement weather delays, PSE&G anticipate working Monday through Friday (7:00am - 7:00pm). Limited lane or road closures will occur during working hours.

    Safety is our primary concern. PSE&G will work with the Paramus Police Department to minimize any traffic concerns or inconveniences to the public. During construction, please refrain from going near our construction work zones.

June 23, 2017

PSE&G to Begin Electric Reliability Work in Hoboken

(Newark, NJ – June 23, 2017)  Public Service Electric and Gas Co. (PSE&G), New Jersey’s largest utility, will begin construction on new critical underground electrical infrastructure in Hoboken as part of the utility’s Madison Street Substation Project. This work is part of the overall plan for the station that will ensure safe, reliable electric service for residents and businesses in the area. Construction is planned to begin on or around Monday, June 26, 2017 and will continue through December of 2017.

On or around June 26th, u... Continue Reading

August 27, 2014

Rutgers Study: PSE&G is an Economic Engine for New Jersey
Transmission upgrades responsible for creating 6,000 jobs annually from 2011-2021

(Newark, NJ – August 27, 2014) – From 2011 to 2021, Public Service Electric and Gas Company (PSE&G) investments in New Jersey’s electric transmission network will be a powerful stimulant of the state’s economy, according to an analysis by Rutgers University. The report, released today, concludes the company’s 10-year, $8.1 billion transmission investment program will support 6,000 jobs annually -- generating more than $4.3 billion in salary and benefits and... Continue Reading