Hasbrouck Heights

Reliability Project Overview

PSE&G is currently conducting statewide electric reliability improvements to its utility infrastructure. These enhancements will improve both electric service reliability and system redundancy to ensure safe and reliable service to our customers. Throughout the state of New Jersey, PSE&G infrastructure upgrades will reduce the demand on the existing 26kV network. The projects will install 69kV transmission circuits connecting PSE&G stations around the state.

Activity Overview

Construction of a new, 69kV substation began the first quarter of 2019. The facility will enhance the electric transmission system's reliability, while helping to ensure safe service to residents and businesses in Harrison and neighboring communities.

Completed installation of new 69kV utility poles to connect Hasbrouck Heights (via Wood-Ridge and Moonachie) to Carlstadt. Project also completed a two-story, gas-insulated switchgear (GIS) building and control house in 2020.

The addition of a new 69kV supply source to the South 5th Street substation will not only simplify operations and improve reliability, it will also ensure adequate capacity for future growth.
 

For questions, please contact our Project Headline at 1-800-901-5035.

For more information on this project, please contact:

Project Hotline - North
1-800-901-5035
Image CAPTCHA
Enter the characters shown in the image.

For media inquiries regarding this project, please contact:

PSE&G's Media Hotline
973-430-7734