Back to top

Garfield

Activity Overview                                               

  • New 69kV circuits will connect the Plauderville Substation and the Passaic Substation.
  • New 69kV circuits will connect the Plauderville Substation and the East Rutherford Substation.
  • The existing utility poles will be replaced with taller, sturdier poles that combine new 69kV circuits with existing 26kV, 13kV, or 4kV circuits.
  • Vegetation Management activity such as tree trimming or tree removals may occur in order to allow for the safe installation of new equipment.
  • Pole line reconstruction commenced in the 3rd Quarter of 2021.
  • The project is estimated to be completed by the 3rd Quarter of 2022.
  • PSE&G will work with the City of Garfield Police to keep traffic impacts to a minimum.

For more information on this project, please contact:

Project Hotline - North
1-800-901-5035
Image CAPTCHA
Enter the characters shown in the image.

For media inquiries regarding this project, please contact:

PSE&G's Media Hotline
973-430-7734