  • New 69kV circuits will connect the Plauderville Substation and the Passaic Substation.
  • New 69kV circuits will connect the Plauderville Substation and the East Rutherford Substation.
  • New 69kv circuits will connect the Plauderville Substation to the Maywood Substation.
  • The existing utility poles will be replaced with taller, sturdier poles that combine new 69kV circuits with existing 26kV, 13kV, or 4kV circuits.
  • Vegetation Management activity such as tree trimming or tree removals may occur in order to allow for the safe installation of new equipment.
  • Pole line reconstruction commenced in the 3rd Quarter of 2021.
  • The project is estimated to be completed by the 3rd Quarter of 2022.
  • PSE&G will work with the town police to keep traffic impacts to a minimum.

For more information on this project, please contact:

Project Hotline - North (Bergen, Passaic)
1-800-901-5035
Image CAPTCHA
Enter the characters shown in the image.

For media inquiries regarding this project, please contact:

PSE&G's Media Hotline
973-430-7734

NOTE: Construction schedule information is tentative and subject to change based on several factors, including weather and field conditions.

Q4 2022

Starting the first week of October 2022 PSE&G will be upgrading and replacing utility poles along the following streets:

  • Midland Avenue  (Between Stefanic Avenue and Market Street )
  • Market Street (Between Midland Avenue and Saddle River Road
  • Saddle River Road (Between Market Street and Ackerman Street)
  • Railroad Avenue (Between Saddle River Road and Rochelle Avenue)
  • Rochelle Avenue (Between Railroad Avenue and Central Avenue)
  • Central Avenue (Between Rochelle Avenue and 156 W. Central Avenue