69kV Statewide Initiative

Public Service Electric & Gas Co. (PSE&G), New Jersey’s largest utility, is committed to delivering safe, reliable electric service to its customers. Maintaining world-class reliability requires an electric infrastructure that can keep pace with customers’ evolving energy needs. Over the last several decades, New Jersey has experienced tremendous commercial and residential growth. As businesses and residents use more electricity, it is our responsibility to reinforce, upgrade, and in many cases replace, our electric transmission infrastructure to keep up with that demand.

In order to meet existing electric needs, and be better prepared for Sandy-like storms, PSE&G is re-wiring its local power system to create the electric infrastructure of the future by increasing system capacity, enhancing system reliability, and providing greater system redundancy for our customers.

PSE&G is investing approximately $1.28 billion over the next three years [see Forward Looking statement] to replace or supplement its 50-plus-year-old 26kV lines to bring 69kV power throughout the state.  These projects are done either within existing substations and switching stations, or through the construction of new stations, and include installing and replacing overhead lines. The enhanced power lines will be carried on taller, sturdier replacement poles along existing routes.

Spanning from 2007 through 2017, PSE&G has installed approximately 331 miles of 69kV lines in more than 60 New Jersey municipalities to ensure that the people of New Jersey have the power they need when they need it today and for decades to come.

For more information on this project, please contact:

Project Hotline
1-800-901-5035
Kevin Kimbo
1-800-606-0045

For media inquiries regarding this project, please contact:

PSE&G's Media Hotline
973-430-7734
Image CAPTCHA
Enter the characters shown in the image.
    1. What is 69kV transmission?
    2. What will these projects do?
    3. Why are these upgrades needed?
    4. What type of construction will these projects entail?
    5. How tall will the replacement poles be?
    6. What is the difference between the existing and new line voltage?
    7. How long will construction last?
    8. How will this impact traffic?
    9. What are the benefits to the region?
    10. What approvals are you seeking?
    11. Do the lines produce electric and magnetic fields?
    12. Are electric and magnetic fields (EMFs) harmful?
    13. Who can I contact for more information?

    What is 69kV Transmission?

    69kV transmission lines are the standard of the 21st century, linking higher voltage lines with switching stations and substations. They will ultimately replace and enhance a 50+ year-old system built on 26kV lines, increasing reliability, capacity, and safety.

    What will these projects do?

    PSE&G is currently improving its electric reliability statewide in-order to upgrade its utility infrastructure. PSE&G infrastructure upgrades include the addition of a 69kV network that will alleviate the demand on the existing 26kV network. These upgrades will increase both electric service reliability and system redundancy to ensure safe and reliable electric service to our customers.

    Why are these upgrades needed?

    These upgrades are needed to address the increased demand for reliable electricity throughout PSE&G service territory. As population has increased and consumer electronic needs have evolved, the 26kV legacy networks of the last century have been taxed. The addition of a 69kV network will alleviate the demands on the existing 26kV network.

    What type of construction will these projects entail?

    These projects will install 69kV circuits connecting stations to each other. Underground and Overhead pole line construction is taking place throughout the state. New 69kV circuits are being installed to connect each upgraded station and existing utility poles will be replaced with taller sturdier poles that combine existing 26kV, 13kV, or 4kV circuits. New 69kV Gas Insulator Switchgear (GIS) will also be installed at various stations in multiple municipalities.

    How tall will the replacement poles be?

    The replacement poles will range in height between 57 and 65 feet.

    What is the difference between the existing and new line voltage?

    Existing pole lines throughout the state carry 4kV, 13kV and/or 26kV lines. The new pole lines will carry these existing lines in addition to a new 69kV line for added reliability and capacity.

    How long will construction last?

    As of December 17, 2014 PSE&G has augmented or replaced approximately 209 miles of its 26kV network with 69kV lines in several New Jersey municipalities, all in an effort to ensure that the people of New Jersey have the power they need when they need it. Continued substation and pole line construction is currently scheduled through 2021.

    How will this impact traffic?

    Traffic may be slightly impacted during construction; however PSE&G will work with municipal safety and traffic departments to minimize any traffic issues that arise during construction.

    Safety of the public and construction crews is our highest priority. During construction, it is essential that you and anyone occupying your property, including children and pets, refrain from going near our construction work zones.

    What are the benefits to the region?

    This project will provide safe, highly reliable service.  It will also create construction jobs, and provide municipal revenue though requisite permits. The enhanced electrical infrastructure will help support regional economic growth.

    What approvals are you seeking?

    PSE&G will secure necessary permits and approvals from local governing authorities wherever construction is taking place, as well as the New Jersey Department of Environmental Protection and other applicable state agencies.

    Do the lines produce electric and magnetic fields?

    Electric and magnetic fields are present wherever there is a flow of electric current, whether in wires in the home, electrical appliances, or power lines. Electric fields are produced by the voltage or electrical pressure in a wire and are present even if an appliance is turned off, as long as it is connected to a source of electric power. Magnetic fields are produced whenever there is a flow of electric current through a wire. Electric and magnetic fields are not visible, like other fields such as a gravitational field or a temperature field.

    Are electric and magnetic fields (EMFs) harmful?

    The overwhelming body of scientific study shows no definitive link between EMF and human health issues. Since 1977, concerns over magnetic fields and possible health effects have been the subject of numerous scientific and regulatory review panels, and extensive research and studies continue to be funded in this field of study.

    After nearly 30 years of worldwide research, there are no direct or causal links between electric and magnetic fields and adverse health effects. New Jersey has standards regarding maximum permissible electric fields at the edge of transmission line rights of way. However, there are no state standards with regards to magnetic field levels nor are there any federal rules, regulations or standards for either electric or magnetic field levels.

    Magnetic fields from appliances like hair dryers, microwave ovens, and motorized appliances are often stronger than the fields directly beneath power lines. PSE&G will design and install this line according to appropriate state and federal guidelines related to safety and environmental impact.

    Learn more about EMF 

    Who can I contact for more information?

    If you have questions or concerns, please visit our website at http://psegtransmission.com/reliability-projects/69kV or call our toll free number at 1-800-901-5035 (for Bergen, Passaic, Hudson, Essex, Morris, Somerset, Union, Hunterdon and Middlesex counties) or 1-800-606-0045 (for Mercer, Burlington, Camden or Gloucester counties).

Plainsboro

12-17-18 through Spring 2019

PSE&G plans to begin upgrading and replacing the utility poles along Dey Road beginning near Pheasant Hollow Drive and continuing to Rt 130.  This work is expected to begin on or around Monday, December 17 and continue intermittently through the spring 2019.  Work will occur between 7:30 a.m. and 4:30 p.m., Monday through Friday, as well as some weekend work, as needed. There are no service outages planned with this work

Bound Brook

May 2017 through August 2017

PSE&G plans to begin upgrading and replacing utility poles along Route 28 (Union Ave) between Tea Street and Green Brook Road, as well as on Tea Street. Work is expected to be completed between 7:30 a.m. and 4:30 p.m., Monday through Friday, as well as some weekend work, as needed. 

Safety is our highest priority. PSE&G will work with the Bound Brook Police Department to minimize any traffic concerns or inconvenience to the public. It is essential that you and anyone using your property, including children and pets, refrain from going near our construction work zones. For construction activities in and on the public right of way, local authorities will provide traffic control to keep both our work crews and the traveling public safe.

There are no planned electric service outages as part of this construction activity. 

Bridgewater

August 14-18 2017

PSE&G will be completing underground construction activity on Main Street between Tea Street (Bound Brook) and STS Drive. Minor traffic changes may be required, including lane shifts. 

Safety is our highest priority. PSE&G is working with the Bridgewater Police Department to minimize any traffic concerns or inconvenience to the public. It is essential that you and anyone using your property, including children and pets, refrain from going near our construction work zones. For construction activities in and on the public right of way, local authorities will provide traffic control to keep both our work crews and the traveling public safe.

Plainfield

Beginning late-January 2018

Overhead construction to upgrade utility poles is expected to begin on or around January 23 on Myrtle Avenue, Everett Place, and West Front Street in the City of Plainfield. Safety is our primary concern. To complete this work safely, PSE&G will work with the City of Plainfield Police Department to minimize any traffic concerns or inconvenience to the public when necessary. Some brief lane or road closures may be required. 

 

Franklin

On or around September 10 2018, PSE&G crews and our approved contractors will begin installing new, upgraded poles on Van Cleef Road between Jean Road and Amwell Road. All work will be completed between 7:30 AM - 4:30 PM, Monday through Friday. Work in this area will be intermittent. 

On or around September 17 2018 and continuing until the end of October, PSE&G and our approved contractors will begin installing new, upgraded poles on working on Elizabeth Avenue between Weston Road and School House Road. 

Safety is our highest priority. PSE&G and our approved contractors will be working with the Franklin Township Police Department to minimize any traffic concerns or inconvenience to the public. It is essential that you and anyone using your property, including children and pets, refrain from going near our construction work zones.

 

 

Dunellen

December 2017 - February 2018

PSE&G will be upgrading and replacing the utility poles along Madison Avenue, Mountain View Terrace, N. Washington Avenue, 1st Ave, Jackson Ave, and Dunellen Avenue.

This work is expected to begin in Dunellen early December and continue, intermittently, throughout early 2018, working between 7:30 a.m. and 4:30 p.m., Monday through Friday, as well as some weekend work, as needed.

To safely complete this work, lane closures and/or brief road closures may be required.

All closures will be coordinated with Dunellen Borough Police Department. 

Ewing

On-Going

Beginning March 2015 and continuing intermittently through Q4 2018, construction work in support of the 69kV upgrades will occur on the following streets in Ewing and Hamilton Township:

  • Federal City Road
  • Upper Ferry Road
  • Scotch Road
  • Parkway Ave
  • N. Olden Ave
  • Arctic Parkway
  • Spruce St
  • Princeton Ave
  • Mulberry St
  • Nottingham Way
  • Rosalie Ave

Work includes installing new poles, installing new 69kV cable and critical electrical equipment, and removal of old poles (please also reference the "Overhead Construction Process" page for additional information). 

Safety is our primary concern. PSE&G will work with the Ewing Police Department to minimize any traffic concerns or inconveniences to the public. During construction, please refrain from going near our construction work zones.

 

Franklin

December 10 - January 7

Crews are currenly working the installation of new poles and overhead construction activity on Van Cleef Road, and will be moving to Amwell Road between Van Cleef Road and Elizabeth Avenue on or around December 10 and continue intermittently for 4-6 weeks.  All work will be completed between 7:30 a.m. and 4:30 p.m., Monday through Friday, as well as some weekend work, as needed. Safety is our highest priority. PSE&G and our approved contractors will be working with the Franklin Township Police Department to minimize any traffic concerns or inconvenience to the public.  There are no planned outages associated with this work.

Green Brook

Fall 2018

PSE&G will be completing the transfer of equipment from old poles onto new poles throughout Green Brook, working with local police for traffic control as needed. 

 

 

 

 

Hamilton

June 1, 2017 through July 31, 2017

Vegetation management activity, pole setting, wire work and equipment transfer will take place intermittently through May on the following streets in Hamilton Township:

  • White Horse Mercerville Rd.
  • Klockner Rd.

Work includes installing new poles, installing new 69kV cable and critical electrical equipment, and removal of old poles (please also reference the "Overhead Construction Process" page for additional information). 

Safety is our primary concern. PSE&G will work with the Ewing and Hamilton Police Departments to minimize any traffic concerns or inconveniences to the public. During construction, please refrain from going near our construction work zones.

Hoboken

Beginning in December 2018:
Work crews are scheduled to begin setting new, 69kV utility poles along Madison Street, from Observer Highway to the Madison Street Substation on 12th Street.

For questions or more information about the project, please call PSE&G’s Electric Reliability Hotline at 1-800-901-5035.

PSE&G will take all necessary steps to avoid any major inconvenience to our customers in the area. However, road and lane closures with possible detours will be necessary during construction. Road closures will not take place prior to 9:00 AM If possible, motorists are encouraged to travel an alternate route until the work is completed. Hoboken Police will be on site during construction hours to oversee and assist with new traffic patterns. All efforts will be made to keep interruptions to a minimum.

Jersey City

Current Construction Activity:

Week of August 13, 2018

  • Crews will install new utility poles along the existing pole line on Seaview Avenue in Jersey City, between Romar Avenue and Old Bergen Road.
  • Crews will begin the installation of new utility poles along the existing pole line on Old Bergen Road from Seaview Avenue to Merritt Street.

For questions or more information about the project, please call PSE&G’s Electric Reliability Hotline at
1-800-901-5035.

Little Falls

July 5, 2017 through December 2017

Pole replacement and overhead construction activity will occur on:

Jean Drive, Ethel Drive, Francisco Ave, Ridge Road, Long Hill Road, and Notch Road

Construction activity will occur predominately Monday-Saturday, between 7:00 a.m. through 3:00 p.m.

During construction, limited lane closures may be required to accommodate safe work and travel conditions. Safety is our primary concern. PSE&G will work with the Little Falls Police Department to minimize any traffic and parking concerns and inconvenience to the public. During construction, please refrain from going near our construction work zones.  

Middlesex

Late April 2018

Underground construction activity has been completed in this area, and PSE&G and our approved contractors will be completing restoration to the affected roadways. Weather dependent, milling activity will begin April 26, 2018 and paving will occur on April 27, 2018. During work hours, no street parking will be permitted and road closures will be required during paving with no vehicle access. Traffic control and detours will be in place during restoration efforts.

Work will occur on the following streets:

  • Green Brook Road between Bound Brook Road and Spring Mills Road
  • Bound Brook Road between Green Brook Road and Locust Avenue

In order to complete this work with minimal impact to your community, police will be directing traffic and motorists will have access to the roads during non-paving hours. We ask that you please adhere to the no parking signs that may be placed on the streets listed above.

Safety is our highest priority. PSE&G will work with the local Police Department to minimize any traffic concerns or inconvenience to the public. It is essential that you and anyone using your property, including children and pets, refrain from going near our construction work zones.

New Milford

New Milford Substation

Civil and electrical construction activity will continue inside the station through. No service outages are expected during this work. 

Due to unexpected changes in construction within the property of the New Milford Substation, PSE&G and its approved contractors will be carrying out additional construction activity on Saturday, May 19 and Sunday, May 20. 

Safety is our primary concern. PSE&G will work with the New Milford Police Department to minimize any traffic concerns or inconveniences to the public. During construction, please refrain from going near our construction work zones.

North Bergen

Summer 2017

Union City Substation

GIS Building work and other construction activities will occur within the station fence line. 

Excluding inclement weather delays and the need for extended hours, PSE&G anticipates working Monday through Friday (7:00am - 6:00pm) and Saturday (10:00am - 6:00pm). Limited road closures may occur and parking restrictions will be in effect during large deliveries. 

Tonnelle Avenue Substation

Electrical and civil construction activity will occur within the station fence line. 

Excluding inclement weather delays, PSE&G anticipates working Monday through Friday (7:00am - 6:00pm) and Saturday (10:00am - 6:00pm).

Safety is our primary concern. PSE&G will work with the North Bergen Police Department to minimize any traffic concerns or inconveniences to the public. During construction, please refrain from going near our construction work zones.

October 23 - December 15

PSE&G anticipates beginning underground construction activities on Hamlin Place, Van Buren Drive, Washington Place and Edlys Lane on or around Monday, October 23, 2017.  Work is expected to be completed in 6-8 weeks (weather dependent).

Lane shifts and detours may be required during construction and will be coordinated with local police and traffic control. 

We do not anticipate this work causing any interruption of your electric service.
 

North Plainfield

2/6/18 - 3/30/18

Overhead construction activity to install new utility poles and upgraded cable will begin on or around February 6 and continue through late March 2018 on Greenbrook Road between Clinton Ave and Grove Street. Brief road or lane closures may be required to safely complete this work. 

All work around West End Elementary School will be completed on weekends to minimize inconvenience and impact.

Safety is our highest priority. PSE&G will work with the North Plainfield Borough Police Department to minimize any traffic concerns or inconvenience to the public. It is essential that you and anyone using your property, including children and pets, refrain from going near our construction work zones. For construction activities in and on the public right of way, local authorities will provide traffic control to keep both our work crews and the traveling public safe.

Rutherford

July 2017 through December 2017

Pole replacement and overhead construction activity will occur on:

Highland Cross, Eastern Way, Pierrepont Avenue, Feronia Way, and Barrows Lane

Construction activity will occur predominately Monday - Friday, between 8:00 a.m. and 4:00 p.m.

During construction, limited lane closures may be required to accommodate safe work and travel conditions. Safety is our primary concern. PSE&G will work with the Rutherford Police Department to minimize any traffic and parking concerns and inconvenience to the public. During construction, please refrain from going near our construction work zones.  

 

South Brunswick

December 17 2018 through Spring 2019

PSE&G plans to begin upgrading and replacing the utility poles along Dey Road beginning near Pheasant Hollow Drive and continuing to Rt 130.  This work is expected to begin on or around Monday, December 17 and continue intermittently through the spring 2019.  Work will occur between 7:30 a.m. and 4:30 p.m., Monday through Friday, as well as some weekend work, as needed. There are no service outages planned with this work.

Trenton

Fall 2017

Pole setting, wire work and equipment transfer will take place intermittently on the following streets in the City of Trenton:

  • Adeline Street
  • Broad Street
  • Clinton Ave

Work includes installing new poles, installing new 69kV cable and critical electrical equipment, and removal of old poles (please also reference the "Overhead Construction Process" page for additional information). 

At the same time we are doing the above work we will begin additional electric upgrades in the city of Trenton.

Beginning in September 2017 and continuing intermittently through May 2018, PSE&G will be replacing utility poles throughout the City of Trenton.  This work is part of the Fernwood Network Upgrade to eliminate outdated equipment and upgrade utility poles and equipment where necessary to ensure optimal service for customers. These upgrades will help prepare the area for future utility upgrades as well, to enhance and improve the reliability of PSE&G’s electric service to City of Trenton and the surrounding area.

Work will occur on the following streets:

  • River Road
  • Afton Avenue
  • Sanhican Drive
  • Morningside Drive
  • Abernathy Drive
  • La Barre Avenue
  • Argyle Avenue
  • Mill Road
  • School Lane
  • Shelburne Ave
  • Route 29

Safety is our primary concern. PSE&G will work with the City of Trenton, Ewing and Hamilton Police Departments to minimize any traffic concerns or inconveniences to the public. During construction, please refrain from going near our construction work zones.  It is essential that you and anyone using your property, including children and pets, refrain from going near our construction work zones.

Union Township

December 2018

Beginning in November 2018 and continuing for several months, PSE&G will be completing vegetation maintenance and replacing utility poles throughout Union Township. This work is part of the 69kV upgrade connecting Stanley Terrace Substation and Springfield Road Substation. These upgrades will help to enhance and improve the reliability of PSE&G’s electric service to Union Township and the surrounding area.

Beginning November  2018, PSE&G overhead construction crews and vegetation management contractor crews will begin working on Morrison Ave between Stuyvesant Avenue and Winslow Avenue. PSE&G anticipates continuing work on Winslow Avenue, Commerce Avenue, Morris Avenue, and Rahway Avenue throughout 2019. Work will occur intermittently at each location and police will be on-site during all activity to ensure safe traffic operations and minimal inconvenience.

Beginning on or around December 3, PSE&G anticipates beginning underground construction activities on Springfield Road between Milltown Road and Route 22. Work will occur from 7:00 PM to 6:00 AM and will require a road closure. Work is expected to be completed in 1 week. 

There are no planned electric service outages affiliated with this work

Safety is our highest priority. PSE&G will work with the Union Township Police Department to minimize any traffic concerns or inconvenience to the public. During construction, short-term lane or shoulder closures may be necessary. It is essential that you and anyone using your property, including children and pets, refrain from going near our construction work zones. For construction activities in and on the public right of way, local authorities will provide traffic control to keep both our work crews and the traveling public safe.

Wayne

July 2017 through August 2017

PSE&G plans to begin overhead and underground construction on or around July 5, 2017 and will continue through early-August 2017. Some unavoidable noise will be generated during construction. Construction activities will occur on the following streets:

  • Paterson Hamburg Turnpike between Hinchman Avenue and Ratzer Road
  • University Drive between Hamburg Turnpike and West Overlook
  • West Overlook Avenue and Overlook Avenue to Linda Vista Avenue
  • High Mountain Road between Walray Avenue and Lakeview Avenue

Safety is our highest priority. PSE&G will work with the Wayne and North Haledon Police Departments to minimize any traffic concerns or inconvenience to the public. It is essential that you and anyone using your property, including children and pets, refrain from going near our construction work zones. Local authorities will provide traffic control to keep both our work crews and the traveling public safe, lane closures or detours may be required.

 

June 23, 2017

PSE&G to Begin Electric Reliability Work in Hoboken

(Newark, NJ – June 23, 2017)  Public Service Electric and Gas Co. (PSE&G), New Jersey’s largest utility, will begin construction on new critical underground electrical infrastructure in Hoboken as part of the utility’s Madison Street Substation Project. This work is part of the overall plan for the station that will ensure safe, reliable electric service for residents and businesses in the area. Construction is planned to begin on or around Monday, June 26, 2017 and will continue through December of 2017.

On or around June 26th, u... Continue Reading

August 27, 2014

Rutgers Study: PSE&G is an Economic Engine for New Jersey
Transmission upgrades responsible for creating 6,000 jobs annually from 2011-2021

(Newark, NJ – August 27, 2014) – From 2011 to 2021, Public Service Electric and Gas Company (PSE&G) investments in New Jersey’s electric transmission network will be a powerful stimulant of the state’s economy, according to an analysis by Rutgers University. The report, released today, concludes the company’s 10-year, $8.1 billion transmission investment program will support 6,000 jobs annually -- generating more than $4.3 billion in salary and benefits and... Continue Reading